Arden Service Area Distribution System Pipe Realignment And Meter Installation Project

   ​               Domenchelli.jpg


New - Phase 1A is under construction sign up here to receive project updates by email and text messages!


Background

In 2004, the State Legislature passed Assembly Bill 2572, requiring the installation of water meters by January 1, 2025, as a condition of water service from all water suppliers. To comply with this mandate, SCWA has initiated a multi-phased water meter installation program. The aged and undersized water mains located in the Arden Service Area (ASA) has facilitated pipe material failure and leaks, insufficient fire flows, and various issues for operations and maintenance. The Arden Service Area Distribution System Pipe Realignment and Meter Installation Project (Project) will abandon old pipelines located in backyards, install approximately 38 miles of new distribution pipelines within the street right-of-way, install nearly 3000 new meters, and replace or install new fire hydrants.  Implementing this project will help:

  •  improve reliability
  •  meet current fire flow requirements
  • meet pipeline separation standards; and
  •  lower operation and maintenance costs.

SCWA ASA Overall Phasing Exhibit for website Updated 092818.png 

Tentative Design and Construction Schedule*

SCWA has tentatively scheduled the Project for the following phases for the next seven years:

Project Area           

 Design Timeline              Construction  Timeline  
Phase 1A - Project Page2016 -2017    July 9, ​2018 - March 25, 2019 *New
Phase 2A *NEW​2018-20192019-2020
Phase 2B​​2019-2020​2020-2021
​Phase 1B2020-2021​​2021-2022
​Phase 3​2020-2021​2021-2022
​Phase 4​2021-2022​2022-2023
​Phase 5​2022-2023​2023-2024
​Phase 6​2023-2024​2024-2025

  * Note: Timelines are approximate and are subject to change. Schedule updated as of 09/28/18

SCWA will be providing a Permit for Temporary Entry (PTE) to all customers affected in the project area, per phase. As requested, the PTE developed for the project is available below:

PTE for Arden Service Area Project _Sample

To comply with the California Environmental Quality Act (CEQA), the Sacramento County, Planning and Environmental Review Division prepared a Negative Declaration for the complete Arden Service Area Distribution System Pipe Realignment and Meter Installation Project. The Negative Declaration was posted to the State Clearing House, Sacramento Metro Air Quality Management, Arden/Arcade Community Planning Advisory Council, San Juan Unified School District, Arden-Dimick Community Library and the Sacramento Bee.  The public review period was held between June 6, 2017 to July 6, 2017.  Given recent feedback from the community, SCWA will be providing an additional comment period (35 days) for the Arden Service Area residents who wish to review the documents and provide written comments. SCWA presented the CEQA documentation for approval at the December 12, 2017 Board Meeting.  The direct link to review the CEQA documents can be found using the hyperlink below:

CEQA Negative Declaration

First Notification Letter to ASA Customer

SCWA Water Meter Infrastructure Implementation Plan Pamphlet

For additional information regarding water meters click here .

Project Contacts

Helen Rocha, Project Engineer, (916) 874-3070, ArdenServiceMeters@saccounty.net